Actual (or expected) output = (Effective capacity) (Efficiency) 5.5 cars 0.880 = 4.84 cars. Therefore, in one 8-hour day, one bay accommodates (8 hr 4.84 cars per hr) = 38.72 cars. To do 200 cars per to do for 200 cars = 200 / 38.72 = 5.17 bays ( rounded to 6 )